The R&M of Unit-1 was awarded to M/s BHEL at a negotiated price of Rs. 120
crore. The work of R&M was started on 25.09.2007 and is expected to complete
within the next 5-6 months. The Unit capacity after R&M will increase from
110 MW to 117.8 MW. |
| |
The R&M of 110 MW Unit-2 has already been carried out and the unit is performing
satisfactorily. |
| |
The
R&M of 110 MW Units 3, 4 & 5 shall be carried out after the completion
of R&M of Unit-1, during the 11th Five Year Plan at an approx.
cost of Rs. 500 crores. |
| |
With
the completion of R&M, these old Units of PTPS are expected to generate maximum
cost effective electricity for the State of Haryana.
|
| |
It
has been decided to phase out the 55 MW Units of FTPS Faridabad
by 2011-12 as these Units are very old and of obsolete design and the cost of
generation from these Units is very high. As such no major R&M schemes have
been proposed for FTPS. Only essential R&M works required for sustenance of
these old Units is proposed to be carried out. |