HOME > FUTURE PROJECTS > GAS BASED PROJECTS ....
 

Expression of interest has been received by the State Govt. from many Independent Power Producers (IPPs) and HoA has been signed with M/s GAIL, for setting up gas based plants at various locations in Haryana as shown in the table given below:-

Sr. No.

IPP showing expression of interest

Proposed Sites in Haryana

Capacity proposed by IPP

HOA signed with GAIL on

Implement-ation schedule

1.

M/s Jindal Stainless Ltd., Hisar

Hisar

1080 MW.

06.09.2005

Not firmed up, as gas availability is uncertain.

2.

M/s Weizmann Private Ltd., Mumbai

Panipat

600 MW.

16.09.2005

3.

M/s Tayal Energy, Silvassa.

Panipat

400 MW.

14.10.2005

4.

M/s Tata Power Company / NDPL.

Jhajjar

1000 MW

17.11.2005

5.

M/s Aban Lloyd Chilies offshore Ltd., Chennai.

Faridabad

1065 MW

03.05.2005.

6.

M/s Torrent Private Ltd., Ahmedabad.

Panipat

370 MW

-

Due to the uncertainty in availability of gas, the schedule of implementation has not been firmed up and the State Govt. has not entered into any MoU/ PPA with the above IPPs. 

It was envisaged that whenever the gas position becomes comfortable, these projects will be taken up for implementation. Recently, gas findings in the country have been reported by reputed companies like M/s. Reliance, M/s. GSPC & M/s. ONGC as under:-

Company

Estimated Reserves

Estimated Production

M/s. Reliance

11–14Trillion Cubic Feet (TCF)

34 MMSCMD

M/s GSPC

18 -20 TCF

62 MMSCMD

M/s. ONGC

20 -22 TCF

62 MMSCMD

Efforts are being initiated to set up a 1050 MW Gas Based Power Plant in Faridabad under the State Sector by phasing out the  existing, old/obsolete Coal based 165 MW Power Plant. The gas requirement for this project is expected to be around 5  MMSCMD. Further, the matter is also being taken up with the Ministry of Power, Government of India, to implement the 432 MW Stage-II of NTPC Gas Based Power Plant at Village Mujheri in Faridabad,  the Power from which shall be fully dedicated the State of Haryana. The gas requirement for this project is expected to be around 2.5  MMSCMD.  Possibilities are also being explored for setting up a 600 MW Gas Based Power Project under Second Stage of Yamunanagar Power Project with a gas requirement of 3 MMSCMD.

HPGCL, is also in dialogue with M/s. GAIL, M/s. Reliance, M/s. British Gas, M/s. ONGC etc. for supply of gas for setting up Gas based Power Plant in Haryana. The support of Ministry of Power and the Ministry of Petroleum & Natural Gas is also being solicited.


Copyright © 2004-2007 HPGCL ® All rights reserved. Site Maintained & Developed by Hartron