MW COAL BASED RAJIV GANDHI THERMAL POWER PLANT AT HISAR
|
| | The
work for turnkey implementation of 1200 MW Hisar Thermal Power Project, was awarded
during January, 07. The total estimated cost of the project is Rs.4297 crores.
The cost of Rs. 3.19 crore per MW for this project is the lowest in the Country
and is being talked about as a new benchmark. A Greenfield
project of this size takes at least 39 and 42 months for commissioning. However,
for Hisar project an aggressive commissioning schedule of 35 and 38 months has
been envisaged, which is the shortest commissioning schedule in the country for
such large capacity projects. The State is further targeting a best effort schedule
of 34 and 36 months for early availability of power from these Units. This is
the first project in the Northern Region to be awarded Mega Project status with
attached benefits under the Mega Project policy of Govt. of India. This has resulted
in reduction of project cost and inter-alia lower cost of generation/tariff. With
the commissioning of these two Units, the Haryana
State will be able to provide additional
288 lac units per day to its consumers. The construction work of the project is
going on at full swing. |
|
PROJECT HIGHLIGHTS |
| Installed
Capacity | 2
X 600 MW | | EPC
Cost | Rs
3775.428 crore (total estimated cost Rs.4297 crore) |
| Administrative
approval | 31.12.2005 |
| Detailed
Project Report (DPR) | The
DPR was got prepared from M/s Desein in July, 2006. |
|
Mega Power Status | Granted
on 27.11.2006 by Ministry of Power | |
Equity
contribution | State
Govt. has agreed to contribute 20% of project cost as equity for the project vide
letter dated 22.08.2006. Balance 80% shall be arranged through finance from PFC/REC/NCR
Planning Board. | |
LOI |
Issued
on 29.01.2007 to M/s REL | |
Purchase
Orders & Work Order | Issues
on 10.09.2007 to M/s REL. | |
Contract
Agreement | Signed
on 30.10.2007 with M/s REL | |
Commissioning
Schedule | 600
MW Unit-I December, 2009 (35 Months from LOI) 600
MW Unit-II March, 2010 (38 Months from LOI) |
| Power
Availability | 288
Lac Units Per day | |
Latest
Status | 17.5%
overall progress achieved which includes construction progress of 9.43%. |
|
| POWER
STATION DETAIL |
| Head
of Station | |
Head
of Station | Sh.Arun
Kumar | | Designation
| Chief
Engineer | | Telephone
| 01662-220035,
09416292768 | | Fax
| 01662-223319 |
| Email |
| | Salient
Feature | | Address
1 | H.No.16,
Type-VII | | Address
2 | Vidyut
Nagar, Hisar | | PIN
| 125001 |
| State
| Haryana
| | Approved
Capacity (MW) | 1200
MW | | Installed
Capacity (MW) | 2
Units, each of 600 MW capacity, are being installed. |
| Fuel
Type | Coal
| | Fuel
Source | Mahanadi
Coalfields Ltd., Orissa | |
Water
Source | Barwala
Branch of Bhakhra Canal
| | Beneficiary
State |
|
Haryana
| Common
Pool | Other
States | | 90% |
10% |
-- | | |
Approved
Investment | 4297.00
(Rs.Cr.) | | Unit
Sizes | 2x600
MW | | Date
of Commissioning (dd/mm/yyyy) |
28.12.2009
(Unit-1) & 28.03.2010 (Unit-2) | |
| COAL
BASED PROJECTS UNDER CONSTRUCTION |
| Project
| RGTPP,
Hisar Unit-1 |
State
| Haryana
| Appr.
Capacity | 600
MW | Type
| Coal
| | Project
cost | 2148.50
crore | Target
Date | 28.12.09 |
Main
Plant order Date | 29.01.07 |
|
| | No.
of Unit
| 1 |
|
|
|
|
|
|
| Milestone
| Target
(dd/mm/yyyy) | Actual
(dd/mm/yyyy) | Remarks |
Critical |
| Date
of investment decisions / sanction date | -
| -
| -
| q |
| Order
for Boiler, TG and Auxiliaries |
01.07.2007 |
29.01.2007 | -
| q |
| Order
for Stack | 16.07.2007 |
17.09.2007 | -
| q |
| Commencement
of Boiler foundation work |
16.07.2007 |
19.05.2007 | -
| q |
| Order
for coal handling system |
30.09.2007 |
30.09.2007 | -
| q |
| Order
for CW Pumps / system | 15.10.2007 |
14.09.2007 | -
| q |
| Order
for Cooling Tower | 31.08.2007
| 11.06.2007 | -
| q |
| Commencement
of structural steel erection |
15.01.2008
| 04.01.2008 | -
| q |
| Commencement
of TG foundation | 15.05.2007 |
15.05.2007 | -
| q |
| Order
for WT plant and DM Plant |
01.05.2007 |
15.09.2007
| -
| q |
| Commencement
of Boiler erection | 01.02.2008 | -
| -
| q |
| Boiler
Drum lifting | 28.08.2008 | -
| -
| q |
| Commencement
of condenser erection | 01.11.2008 | -
| -
| q |
| Commencement
of main TG erection | 01.12.2008 | -
| -
| q |
| 1st
Hydraulic Test (drainable parts) |
28.05.2009 | -
| -
| q |
| Readiness
of Chimney | 01.06.2009 | -
| -
| q |
| Boxing
up of TG sets | 15.09.2009 | -
| -
| q |
| Boiler
Light up and alkali boil out |
01.10.2009 | -
| -
| q |
| TG
oil flushing completion |
15.11.2009 | -
| -
| q |
| Boiler
Acid Cleaning completion | -
| -
| -
| q |
| Completion
of Steam Blowing | 22.11.2009
| -
| -
| q |
| TG
on Barring Gear | 16.11.2009 | -
| -
| q |
| Turbine
Rolling | 28.11.2009 | -
| -
| q |
| Synchronisation
| 28.11.2009 | -
| -
| q |
| Coal
Firing | 31.12.2009 | -
| -
| q |
| Completion
of trial oprn, declaration of comml. Oprn |
28.12.2009 | -
| -
| q |
| Boiler
Erection – Tonnage (MT) | -
| -
| -
| q |
|
| COAL
BASED PROJECTS UNDER CONSTRUCTION |
| Project
| RGTPP,
Hisar Unit-2 |
State
| Haryana
| Appr.
Capacity | 600
MW | Type
| Coal
| | Project
cost | 2148.50
crore | Target
Date | 28.03.10 |
Main
Plant order Date | 29.01.07 |
|
| | No.
of Unit
| 1 |
|
|
|
|
|
|
| Milestone
| Target
(dd/mm/yyyy) | Actual
(dd/mm/yyyy) | Remarks |
Critical |
| Date
of investment decisions / sanction date | -
| -
| -
| q |
| Order
for Boiler, TG and Auxiliaries |
01.07.2007 |
29.01.2007 | -
| q |
| Order
for Stack | 16.07.2007 |
17.09.2007 | -
| q |
| Commencement
of Boiler foundation work |
16.10.2007 |
30.09.2007 | -
| q |
| Order
for coal handling system |
30.09.2007 |
30.09.2007 | -
| q |
| Order
for CW Pumps / system |
15.10.2007 |
14.09.2007 | -
| q |
| Order
for Cooling Tower | 31.08.2007
| 11.06.2007 | -
| q |
| Commencement
of structural steel erection |
15.04.2008 |
| -
| q |
| Commencement
of TG foundation | 15.08.2007 |
30.09.2007
| -
| q |
| Order
for WT plant and DM Plant |
01.05.2007 |
15.09.2007
| -
| q |
| Commencement
of Boiler erection | 01.05.2008 | -
| -
| q |
| Boiler
Drum lifting | 28.11.2008 | -
| -
| q |
| Commencement
of condenser erection |
01.02.2009 | -
| -
| q |
| Commencement
of main TG erection | 01.03.2009 | -
| -
| q |
| 1st
Hydraulic Test (drainable parts) |
28.08.2009 | -
| -
| q |
| Readiness
of Chimney | 01.06.2009 | -
| -
| q |
| Boxing
up of TG sets | 15.12.2009 | -
| -
| q |
| Boiler
Light up and alkali boil out |
01.01.2010
| -
| -
| q |
| TG
oil flushing completion |
15.02.2010 | -
| -
| q |
| Boiler
Acid Cleaning completion |
| -
| -
| q |
| Completion
of Steam Blowing | 22.02.2010 | -
| -
| q |
| TG
on Barring Gear | 16.02.2010 | -
| -
| q |
| Turbine
Rolling | 28.02.2010 | -
| -
| q |
| Synchronisation
| 28.02.2010 | -
| -
| q |
| Coal
Firing | 31.03.2010 | -
| -
| q |
| Completion
of trial oprn, declaration of comml. Oprn |
28.03.2010 | -
| -
| q |
| Boiler
Erection – Tonnage (MT) | -
| -
| -
| q |
|
| PROJECTS
YET TO BE AWARDED / PROJECTS UNDER DEVELOPMENT (COAL BASED) |
| Project
| RGTPP |
State
| Haryana
| Appr.
Capacity (MW) | 1200
MW |
| Milestone
| Target
(dd/mm/yyyy) | Actual
(dd/mm/yyyy) | Remarks |
Critical |
| FR
Preparation |
|
|
| q |
| Project
authorization by GENCO / State Govt. | -
| 31.12.2005 |
| q |
| Water
Source & Tie-up | -
| 02.05.2006
| (Barwala
Bhakhra Canal
Branch) | q |
| Fuel
Source & Tie-up | -
| 30.03.2007
& 17.05.2007
| Mahanadi
Coalfields Ltd., Orissa | q |
| EIA
Study Completion | -
| 18.08.06
| In
Envt clearance accorded vide letter dt.20.02.2007 |
q |
| Site
Clearance by MOEF | -
| -
| -
| q |
| Public
Hearing for Envt Clearance | -
| 04.09.2006 | -
| q |
| NOC
from SPCB | -
| 25.10.2006
| -
| q |
| MOEF
Clearance | -
| 20.02.2007
| -
| q |
| Defence
Clearance | -
| Awaited
| -
| q |
| Power
Purchase Agreement | -
| -
| -
| q |
| Financial
Tie-up | -
| -
| -
| q |
| Investment
approval by GENCO / Govt. | -
| 22.08.2006 | -
| q |
| NIT
for Main Plant / EPC | -
| 20.07.2006 | -
| q |
| Order
for Main Plant / EPC | -
| 29.01.2007 | -
| q |
| Other
| -
| -
| -
|
| |
|