 HOME > ONGOING PROJECTS > Hisar Project (1200 MW Rajiv Gandhi Plant)....
 
1200 MW COAL BASED RAJIV GANDHI THERMAL POWER PLANT AT HISAR  
 The work for turnkey implementation of 1200 MW Hisar Thermal Power Project, was awarded during January, 07. The total estimated cost of the project is Rs.4297 crores. The cost of Rs. 3.19 crore per MW for this project is the lowest in the Country and is being talked about as a new benchmark. A Greenfield project of this size takes at least 39 and 42 months for commissioning. However, for Hisar project an aggressive commissioning schedule of 35 and 38 months has been envisaged, which is the shortest commissioning schedule in the country for such large capacity projects. The State is further targeting a best effort schedule of 34 and 36 months for early availability of power from these Units. This is the first project in the Northern Region to be awarded Mega Project status with attached benefits under the Mega Project policy of Govt. of India. This has resulted in reduction of project cost and inter-alia lower cost of generation/tariff. With the commissioning of these two Units, the Haryana State will be able to provide additional 288 lac units per day to its consumers. The construction work of the project is going on at full swing.
PROJECT HIGHLIGHTS

Installed Capacity

2 X 600 MW

EPC Cost

Rs 3775.428 crore (total estimated cost Rs.4297 crore)

Administrative approval

31.12.2005

Detailed Project Report (DPR)

The DPR was got prepared from M/s Desein in July, 2006.

Mega Power Status

Granted on 27.11.2006 by Ministry of Power

Equity contribution

State Govt. has agreed to contribute 20% of project cost as equity for the project vide letter dated 22.08.2006. Balance 80% shall be arranged through finance from PFC/REC/NCR Planning Board.

LOI

Issued on 29.01.2007 to M/s REL

Purchase Orders & Work Order

Issues on 10.09.2007 to M/s REL.

Contract Agreement

Signed on 30.10.2007 with M/s REL

Commissioning Schedule

600 MW Unit-I      December, 2009 (35 Months from LOI) 

600 MW Unit-II     March, 2010 (38 Months from LOI)

Power Availability

288 Lac Units Per day

Latest Status

17.5% overall progress achieved which includes construction progress of 9.43%. 



POWER STATION DETAIL

Head of Station

Head of Station

Sh.Arun Kumar

Designation

Chief Engineer

Telephone

01662-220035, 09416292768

Fax

01662-223319

Email

Salient Feature

Address 1

H.No.16, Type-VII

Address 2

Vidyut Nagar, Hisar

PIN

125001

State

Haryana

Approved Capacity (MW)

1200 MW

Installed Capacity (MW)

2 Units, each of 600 MW capacity, are being  installed.

Fuel Type

Coal

Fuel Source

Mahanadi Coalfields Ltd., Orissa

Water Source

Barwala Branch of Bhakhra Canal

Beneficiary State

Haryana

Common Pool

Other States

90%

10%

    --

Approved Investment

4297.00       (Rs.Cr.)

Unit Sizes

2x600 MW

Date of Commissioning (dd/mm/yyyy)

28.12.2009 (Unit-1)  & 28.03.2010 (Unit-2)

 

 COAL BASED PROJECTS UNDER CONSTRUCTION

Project

RGTPP, Hisar

Unit-1

State

Haryana

Appr. Capacity

600 MW

Type

Coal

Project cost 

2148.50 crore

Target Date

28.12.09

Main Plant order Date

29.01.07

No. of

Unit

1

Milestone

Target (dd/mm/yyyy)

Actual (dd/mm/yyyy)

Remarks

Critical

Date of investment decisions / sanction date

- - -

q

Order for Boiler, TG and Auxiliaries

01.07.2007

29.01.2007

-

q

Order for Stack

16.07.2007

17.09.2007

-

q

Commencement of Boiler foundation work 

16.07.2007

19.05.2007

-

q

Order for coal handling system

30.09.2007

30.09.2007

-

q

Order for CW Pumps / system

15.10.2007

14.09.2007

-

q

Order for Cooling Tower

31.08.2007

11.06.2007

-

q

Commencement of structural steel erection

15.01.2008

04.01.2008

-

q

Commencement of TG foundation

15.05.2007

15.05.2007

-

q

Order for WT plant and DM Plant

01.05.2007

15.09.2007

-

q

Commencement of Boiler erection

01.02.2008

- -

q

Boiler Drum lifting

28.08.2008

- -

q

Commencement of condenser erection

01.11.2008

- -

q

Commencement of main TG erection

01.12.2008

- -

q

1st Hydraulic Test (drainable parts)

28.05.2009

- -

q

Readiness of Chimney

01.06.2009

- -

q

Boxing up of TG sets

15.09.2009

- -

q

Boiler Light up and alkali boil out

01.10.2009

- -

q

TG oil flushing completion 

15.11.2009

- -

q

Boiler Acid Cleaning completion

- - -

q

Completion of Steam Blowing

22.11.2009

- -

q

TG on Barring Gear

16.11.2009

- -

q

Turbine Rolling

28.11.2009

- -

q

Synchronisation

28.11.2009

- -

q

Coal Firing

31.12.2009

- -

q

Completion of trial oprn, declaration of comml. Oprn

28.12.2009

- -

q

Boiler Erection – Tonnage (MT)

- - -

q

COAL BASED PROJECTS UNDER CONSTRUCTION
Project
RGTPP, Hisar Unit-2
State
Haryana
Appr. Capacity
600 MW
Type
Coal

Project cost 

2148.50 crore

Target Date

28.03.10

Main Plant order Date

29.01.07

No. of

Unit

1

Milestone

Target (dd/mm/yyyy)

Actual (dd/mm/yyyy)

Remarks

Critical

Date of investment decisions / sanction date

- - -

q

Order for Boiler, TG and Auxiliaries

01.07.2007

29.01.2007

-

q

Order for Stack

16.07.2007

17.09.2007

-

q

Commencement of Boiler foundation work 

16.10.2007

30.09.2007

-

q

Order for coal handling system

30.09.2007

30.09.2007

-

q

Order for CW Pumps / system

15.10.2007

14.09.2007

-

q

Order for Cooling Tower

31.08.2007

11.06.2007

-

q

Commencement of structural steel erection

15.04.2008

 

-

q

Commencement of TG foundation

15.08.2007

30.09.2007

-

q

Order for WT plant and DM Plant

01.05.2007

15.09.2007

-

q

Commencement of Boiler erection

01.05.2008

- -

q

Boiler Drum lifting

28.11.2008

- -

q

Commencement of condenser erection

01.02.2009

- -

q

Commencement of main TG erection

01.03.2009

- -

q

1st Hydraulic Test (drainable parts)

28.08.2009

- -

q

Readiness of Chimney

01.06.2009

- -

q

Boxing up of TG sets

15.12.2009

- -

q

Boiler Light up and alkali boil out

01.01.2010

- -

q

TG oil flushing completion 

15.02.2010

- -

q

Boiler Acid Cleaning completion

- -

q

Completion of Steam Blowing

22.02.2010

- -

q

TG on Barring Gear

16.02.2010

- -

q

Turbine Rolling

28.02.2010

- -

q

Synchronisation

28.02.2010

- -

q

Coal Firing

31.03.2010

- -

q

Completion of trial oprn, declaration of comml. Oprn

28.03.2010

- -

q

Boiler Erection – Tonnage (MT)

- - -

q

PROJECTS YET TO BE AWARDED / PROJECTS UNDER DEVELOPMENT (COAL BASED)

Project

RGTPP

State

Haryana

Appr. Capacity (MW)

1200 MW

Milestone
Target (dd/mm/yyyy)
Actual    (dd/mm/yyyy)
Remarks
Critical

FR Preparation

q

Project authorization by GENCO / State Govt.

-

31.12.2005

q

Water Source & Tie-up

-

02.05.2006

(Barwala Bhakhra Canal  Branch)

q

Fuel Source & Tie-up

-

30.03.2007 &

17.05.2007

Mahanadi Coalfields Ltd., Orissa

q

EIA Study Completion

-

18.08.06

In Envt clearance accorded vide letter dt.20.02.2007

q

Site Clearance by MOEF

- - -

q

Public Hearing for Envt Clearance

-

04.09.2006

-

q

NOC from SPCB

-

25.10.2006

-

q

MOEF Clearance

-

20.02.2007

-

q

Defence Clearance 

-

Awaited

-

q

Power Purchase Agreement

- - -

q

Financial Tie-up

- - -

q

Investment approval by GENCO / Govt.

-

22.08.2006

-

q

NIT for Main Plant / EPC

-

20.07.2006

-

q

Order for Main Plant / EPC

-

29.01.2007

-

q

Other

- - -

 