HOME > ONGOING PROJECTS > JHAJJAR PROJECTS....
3X500 ARAVALI SUPER THERMAL POWER PROJECT, JHAJJAR:
 his Coal based Super Thermal Power Project is being Set up at Jhajjar.  The Project is being executed by NTPC from concept to commissioning and subsequent Operation & Maintenance in Joint Venture with Government of Delhi and Government of Haryana.  The MOU in this regard was signed between NTPC, Government of National Capital Territory (NCT), Delhi and Government of Haryana on 24.08.2006.  The best efforts Commissioning Schedule of three Units under this Project is 35, 38 & 41 months.  The Joint Venture Agreement for execution of this Project was signed on 14.12.2006 and the Joint Venture Company  i.e. Aravali Power Company Pvt. Ltd. for execution of this Project, was found on 21.12.2006.  
PROJECT HIGHLIGHTS
 

Installed Capacity

3 X 500 MW

Total estimated cost

Rs 7892.42 crore

Haryana’s Share    

750 MW

Equity contribution

NTPC-50%, Haryana-25%, Delhi-25%.

Date of LOI of Boiler &Turbine

06.07.07 & 14.07.07 repectively.

Power Availability

180 Lac Units Per day

Commissioning Schedule

Generation Expected to commence during 2010

COMMISSIONING SCHEDULE
 The commissioning schedule for the three 500 MW Units under this project shall be as under:
 
1.
500 MW Unit-I:15.04.2010
 
2.
500 MW Unit-II: 15.06.2010.
 
3.
500 MW Unit-III:15.08.2010.
 