Mara
II Mahan coal block of Madhya Pradesh Allocated
jointly to GNCT, Delhi and HPGCL under Government Company dispensation in pursuance
of Section 3(3) (a) (i) of the Coal Mines (Nationalization) Act 1973 on 2nd August,
2006.The total area of Coal block is around 53 sq. Km with Coal bearing area of
30 sq. Km. Coal reserves in this Coal block is 955.96 million tonne underground
Coal reserve varying in grade from A to F. Progress:
A team comprising
of officials from IPGCL, GNCTD & HPGCL visited CMPDIL Ranchi on 25.09.2006
to discus with CMPDIL officers the modalities to be adopted for developing Coal
block. Application
filed with State Mining Deptt., Madhya Pradesh on 01.11.2006 for issuing prospecting
license . Application
submitted to Divisional Forest Officer (Distt. Sidhi) on 02.11.2006 for topographical
and geographical survey
Collected the relevant land details and cadestal map of 8 villages in the coal
block area Mara II Mahan on 23.03.2007 after depositing the revenue fee to concerned
authority and submitted the same to Mining Officer at Sidhi, Madhya Pradesh.
Administrative approval
for development of coal block Mara II Mahan was accorded on 29.03.2007
Discussions held with
M/s Mineral Exploration Corp. Ltd. (MECL), Nagpur on 30.03.2007 regarding preparation
of GR and exploration of coal block.
Offer for Exploration of the Coal Block was received from M/s MECL, Nagpur on
17.04.2007 MoC
was requested on11.05.2007 to make Regional Exploration Report from CMPDI, Ranchi
available free of cost to HPGCL/ GNCT, Delhi to get examined techno commercial
proposition of this coal block.
Govt. of NCT Delhi informed MoC on 16.08.2007 about surrendering the coal block
Mara II Mahan
Meeting held between HPGCL & MECL on 20.08.2007 to review the strategy for
exploration of coal block Mara II Mahan based on the provisional GR report being
obtained from CMPDI on 27.11.2007 and it was suggested to go for mining of the
block covering approx. 10 sqKm in first phase and subsequently balance two blocks
of approx 10 sqKm each in second third phase.
A meeting was made with Secretary Energy MP on 06.12.2007 to explore the modalities
for setting up of Pit-Head Power Project for this Coal block FC
(Power) accorded the approval for the following : a) To approve
priority exploration to be carried out by M/s MECL, Nagpur (A Govt. of India undertaking)
at the rates indicated in their offer dated 17/04/2007. b) To engage
Mecon, Ranchi (A Govt. of India undertaking) to carryout EIA / EMP study, permission
from MoE&F, preparation and sanction of mine plan and preparation of FR for
coal mining. c) To engage RQF to facilitate preparation and sanction
of mine plan under requirement of MoC and to assist during exploration and mining
of the block.
Chief Minister, Haryana made a request to Prime Minister, India vide DO letter
dated on 09.01.2008 for exclusively allocation of Mara II Mahan coal block to
Haryana |