STATE SECTOR PROJECTS:
i. 600 MW (2x300 MW) ONGOING COAL BASED DCRTPP,YAMUNANAGAR.
Project
Highlights:
| Installed
Capacity | 2
X 300 MW |
| EPC
Cost | Rs
2097 crore ( Total estimated cost Rs.2400 crore) |
| Administrative
approval | 22.07.2002 |
| Project
Consultancy | M/s
Desein was appointed Project Consultant on 09.04.2003 and CEA were engaged as
Review Consultants in Jan 2004. |
|
Status of Clearances
: |
|
|
a) Land availability |
Land measuring 1107 acres acquired by erstwhile HSEB near village Ratanpura in
Distt. Yamuna Nagar during 1983-86 period. |
|
b) Water availability |
The Haryana Irrigation Dept. has sanctioned 20 cusecs of water from WJC on 11.03.2003.
|
|
c) NOC from Haryana State
Pollution Control Board (HSPCB) |
The HSPCB has issued
NOC on 09.07.2004. |
|
d) MoE&F clearance
|
The Environment clearance was received from MoE&F in Nov., 2004 |
|
e) Chimney height clearance from Airport Authority of India |
Airport Authority
of India (AAI) issued NOC for construction of 275 M high chimney. The validity
of the NOC was 4 years from 16.07.2002. The AAI have issued the fresh NOC on 08.03.2007.
|
|
f) Coal linkage |
The Ministry of Coal granted coal linkage to the tune of 2.25 MTPA for 2x250 MW
YTPP, Stage-II. Since the project was awarded to M/s REL for turnkey implementation
with capacity of 2x300 MW, Ministry of Coal was requested to enhance the coal
linkage from 2.25 MTPA to 3.00 MTPA. In view of the enhanced
capacity of Project from 2 X 250 MW to 2 X 300 MW, 0.52 MTPA additional coal linkage
has been granted by Ministry of Coal in SLC meeting on 20.12.2006 and for balance
quantity of 0.23 MTPA, matter has been taken up with Ministry of Coal. |
| Equity
contribution |
State Govt. is contributing 20% equity for the project vide letter dated 10.10.2002.
Balance 80% has been arranged through PFC. |
|
Issue of LOI |
Issued to M/s REL
vide letter dated 30.09.2004 |
|
Revised Zero date
of Project |
20.08.2005 |
| Expected
Commissioning Schedule |
300 MW Unit – I 14.06.2008 300 MW Unit – II 20.06.2008 |
b)
Latest
Status of 2x300 MW DCRTPP, Yamunanagar ending March,2008
Unit
– I:
· Boiler
lighted up on 25.08.07 and Unit synchronized on Oil on 13.11.07.
· Full
load on coal firing achieved on 03.02.2008.
·
The Unit is under Trial Operation w.e.f. 31.03.2008.
·
PG Test is scheduled from 23.05.2008 to 14.06.2008.
· Provisional
taking over after successful completion of PG Test.
·
Final taking over after completion of all punch list points.
Unit
– II:
· Boiler
light up done on 30.12.2007
·
Unit synchronized on Oil on 29.03.2008.
·
Coal firing is likely to commence from 20.04.2008.
·
The Trial operation of Unit is expected to commence from 27.04.2008 and completed
by 17.05.2008.
·
Provisional taking over after successful PG test is expected by 20.06.2008.
c)
Financial Progress:
Expenditure
to the tune of Rs.1684.00 crore has been incurred so far against EPC cost of Rs.2097.00
crore
ii.
1200 MW COAL BASED PLANT AT HISAR :
The
work for turnkey implementation of 1200 MW Hisar Thermal Power Project, was awarded
during January, 07. The total estimated cost of the project is Rs.4297 crores.
The cost of Rs. 3.19 crore per MW for this project is the lowest in the Country
and is being talked about as a new benchmark. A Greenfield
project of this size takes at least 39 and 42 months for commissioning. However,
for Hisar project an aggressive commissioning schedule of 35 and 38 months has
been envisaged, which is the shortest commissioning schedule in the country for
such large capacity projects. The State is further targeting a best effort schedule
of 34 and 36 months for early availability of power from these Units. This is
the first project in the Northern Region to be awarded Mega Project status with
attached benefits under the Mega Project policy of Govt. of India. This has resulted
in reduction of project cost and inter-alia lower cost of generation/tariff. With
the commissioning of these two Units, the Haryana
State will be able to provide additional
288 lac units per day to its consumers. The construction work of the project is
going on at full swing.
Project
Highlights:
| Installed
Capacity | 2
X 600 MW |
| EPC
Cost | Rs
3775.428 crore (total estimated cost Rs.4297 crore) |
| Administrative
approval | 31.12.2005 |
| Detailed
Project Report (DPR) | The
DPR was got prepared from M/s Desein in July, 2006. |
|
Mega Power Status | Granted
on 27.11.2006 by Ministry of Power |
|
Equity
contribution | State
Govt. has agreed to contribute 20% of project cost as equity for the project vide
letter dated 22.08.2006. Balance 80% shall be arranged through finance from PFC/REC/NCR
Planning Board. |
|
LOI |
Issued
on 29.01.2007 to M/s REL |
|
Purchase
Orders & Work Order | Issues
on 10.09.2007 to M/s REL. |
|
Contract
Agreement | Signed
on 30.10.2007 with M/s REL |
|
Commissioning
Schedule | 600
MW Unit-I December, 2009 (35 Months from LOI) 600
MW Unit-II March, 2010 (38 Months from LOI) |
| Power
Availability | 288
Lac Units Per day |
|
Latest
Status | 17.5%
overall progress achieved which includes construction progress of 9.43%. |
| POWER
STATION DETAIL |
| Head
of Station | |
Head
of Station | Sh.Arun
Kumar | | Designation
| Chief
Engineer | | Telephone
| 01662-220035,
09416292768 | | Fax
| 01662-223319 |
| Email |
| | Salient
Feature | | Address
1 | H.No.16,
Type-VII | | Address
2 | Vidyut
Nagar, Hisar | | PIN
| 125001 |
| State
| Haryana
| | Approved
Capacity (MW) | 1200
MW | | Installed
Capacity (MW) | 2
Units, each of 600 MW capacity, are being installed. |
| Fuel
Type | Coal
| | Fuel
Source | Mahanadi
Coalfields Ltd., Orissa | |
Water
Source | Barwala
Branch of Bhakhra Canal
| | Beneficiary
State |
|
Haryana
| Common
Pool | Other
States | | 90% |
10% |
-- | | |
Approved
Investment | 4297.00
(Rs.Cr.) | | Unit
Sizes | 2x600
MW | | Date
of Commissioning (dd/mm/yyyy) |
28.12.2009
(Unit-1) & 28.03.2010 (Unit-2) | |
| COAL
BASED PROJECTS UNDER CONSTRUCTION |
| Project
| RGTPP,
Hisar Unit-1 |
State
| Haryana
| Appr.
Capacity | 600
MW | Type
| Coal
| | Project
cost | 2148.50
crore | Target
Date | 28.12.09 |
Main
Plant order Date | 29.01.07 |
|
| | No.
of Unit
| 1 |
|
|
|
|
|
|
| Milestone
| Target
(dd/mm/yyyy) | Actual
(dd/mm/yyyy) | Remarks |
Critical |
| Date
of investment decisions / sanction date | -
| -
| -
| q |
| Order
for Boiler, TG and Auxiliaries |
01.07.2007 |
29.01.2007 |
| q |
| Order
for Stack | 16.07.2007 |
17.09.2007 |
| q |
| Commencement
of Boiler foundation work |
16.07.2007 |
19.05.2007 |
| q |
| Order
for coal handling system |
30.09.2007 |
30.09.2007 |
| q |
| Order
for CW Pumps / system | 15.10.2007 |
14.09.2007 |
| q |
| Order
for Cooling Tower | 31.08.2007
| 11.06.2007 |
| q |
| Commencement
of structural steel erection |
15.01.2008
| 04.01.2008 |
| q |
| Commencement
of TG foundation | 15.05.2007 |
15.05.2007 |
| q |
| Order
for WT plant and DM Plant |
01.05.2007 |
15.09.2007
|
| q |
| Commencement
of Boiler erection | 01.02.2008 | -
| -
| q |
| Boiler
Drum lifting | 28.08.2008 | -
| -
| q |
| Commencement
of condenser erection | 01.11.2008 | -
| -
| q |
| Commencement
of main TG erection | 01.12.2008 | -
| -
| q |
| 1st
Hydraulic Test (drainable parts) |
28.05.2009 | -
| -
| q |
| Readiness
of Chimney | 01.06.2009 | -
| -
| q |
| Boxing
up of TG sets | 15.09.2009 | -
| -
| q |
| Boiler
Light up and alkali boil out |
01.10.2009 | -
| -
| q |
| TG
oil flushing completion |
15.11.2009 | -
| -
| q |
| Boiler
Acid Cleaning completion | -
| -
| -
| q |
| Completion
of Steam Blowing | 22.11.2009
| -
| -
| q |
| TG
on Barring Gear | 16.11.2009 | -
| -
| q |
| Turbine
Rolling | 28.11.2009 | -
| -
| q |
| Synchronisation
| 28.11.2009 | -
| -
| q |
| Coal
Firing | 31.12.2009 | -
| -
| q |
| Completion
of trial oprn, declaration of comml. Oprn |
28.12.2009 | -
| -
| q |
| Boiler
Erection – Tonnage (MT) | -
| -
| -
| q |
|
| COAL
BASED PROJECTS UNDER CONSTRUCTION |
| Project
| RGTPP,
Hisar Unit-2 |
State
| Haryana
| Appr.
Capacity | 600
MW | Type
| Coal
| | Project
cost | 2148.50
crore | Target
Date | 28.03.10 |
Main
Plant order Date | 29.01.07 |
|
| | No.
of Unit
| 1 |
|
|
|
|
|
|
| Milestone
| Target
(dd/mm/yyyy) | Actual
(dd/mm/yyyy) | Remarks |
Critical |
| Date
of investment decisions / sanction date | -
| -
| -
| q |
| Order
for Boiler, TG and Auxiliaries |
01.07.2007 |
29.01.2007 | -
| q |
| Order
for Stack | 16.07.2007 |
17.09.2007 | -
| q |
| Commencement
of Boiler foundation work |
16.10.2007 |
30.09.2007 | -
| q |
| Order
for coal handling system |
30.09.2007 |
30.09.2007 | -
| q |
| Order
for CW Pumps / system |
15.10.2007 |
14.09.2007 | -
| q |
| Order
for Cooling Tower | 31.08.2007
| 11.06.2007 | -
| q |
| Commencement
of structural steel erection |
15.04.2008 |
| -
| q |
| Commencement
of TG foundation | 15.08.2007 |
30.09.2007
| -
| q |
| Order
for WT plant and DM Plant |
01.05.2007 |
15.09.2007
| -
| q |
| Commencement
of Boiler erection | 01.05.2008 | -
| -
| q |
| Boiler
Drum lifting | 28.11.2008 | -
| -
| q |
| Commencement
of condenser erection |
01.02.2009 | -
| -
| q |
| Commencement
of main TG erection | 01.03.2009 | -
| -
| q |
| 1st
Hydraulic Test (drainable parts) |
28.08.2009 | -
| -
| q |
| Readiness
of Chimney | 01.06.2009 | -
| -
| q |
| Boxing
up of TG sets | 15.12.2009 | -
| -
| q |
| Boiler
Light up and alkali boil out |
01.01.2010
| -
| -
| q |
| TG
oil flushing completion |
15.02.2010 | -
| -
| q |
| Boiler
Acid Cleaning completion |
| -
| -
| q |
| Completion
of Steam Blowing | 22.02.2010 | -
| -
| q |
| TG
on Barring Gear | 16.02.2010 | -
| -
| q |
| Turbine
Rolling | 28.02.2010 | -
| -
| q |
| Synchronisation
| 28.02.2010 | -
| -
| q |
| Coal
Firing | 31.03.2010 | -
| -
| q |
| Completion
of trial oprn, declaration of comml. Oprn |
28.03.2010 | -
| -
| q |
| Boiler
Erection – Tonnage (MT) | -
| -
| -
| q |
|
| PROJECTS
YET TO BE AWARDED / PROJECTS UNDER DEVELOPMENT (COAL BASED) |
| Project
| RGTPP |
State
| Haryana
| Appr.
Capacity (MW) | 1200
MW |
| Milestone
| Target
(dd/mm/yyyy) | Actual
(dd/mm/yyyy) | Remarks |
Critical |
| FR
Preparation |
|
|
| q |
| Project
authorization by GENCO / State Govt. | -
| 31.12.2005 |
| q |
| Water
Source & Tie-up | -
| 02.05.2006
| (Barwala
Bhakhra Canal
Branch) | q |
| Fuel
Source & Tie-up | -
| 30.03.2007
& 17.05.2007
| Mahanadi
Coalfields Ltd., Orissa | q |
| EIA
Study Completion | -
| 18.08.06
| In
Envt clearance accorded vide letter dt.20.02.2007 |
q |
| Site
Clearance by MOEF | -
| -
| -
| q |
| Public
Hearing for Envt Clearance | -
| 04.09.2006 | -
| q |
| NOC
from SPCB | -
| 25.10.2006
| -
| q |
| MOEF
Clearance | -
| 20.02.2007
| -
| q |
| Defence
Clearance | -
| Awaited
| -
| q |
| Power
Purchase Agreement | -
| -
| -
| q |
| Financial
Tie-up | -
| -
| -
| q |
| Investment
approval by GENCO / Govt. | -
| 22.08.2006 | -
| q |
| NIT
for Main Plant / EPC | -
| 20.07.2006 | -
| q |
| Order
for Main Plant / EPC | -
| 29.01.2007 | -
| q |
| Other
| -
| -
| -
|
| |
| | TOP
 |
|
iii.
3X500 ARAVALI SUPER THERMAL POWER PROJECT, JHAJJAR:
This
Coal based Super Thermal Power Project is being Set up at Jhajjar. The Project
is being executed by NTPC from concept to commissioning and subsequent Operation
& Maintenance in Joint Venture with Government of Delhi and Government of
Haryana. The MOU in this regard was signed between NTPC, Government of National
Capital Territory (NCT), Delhi and
Government of Haryana on 24.08.2006. The best efforts Commissioning Schedule
of three Units under this Project is 35, 38 & 41 months. The Joint Venture
Agreement for execution of this Project was signed on 14.12.2006 and the Joint
Venture Company i.e. Aravali Power Company Pvt. Ltd. for execution
of this Project, was found on 21.12.2006.
PROJECT
HIGHLIGHTS:
| Installed
Capacity | 3
X 500 MW |
| Total
estimated cost | Rs
7892.42 crore |
| Haryana’s
Share | 750
MW |
| Equity
contribution | NTPC-50%,
Haryana-25%, Delhi-25%. |
|
Date
of LOI of Boiler &Turbine |
06.07.07
& 14.07.07 repectively. |
|
Power
Availability | 180
Lac Units Per day |
|
Commissioning
Schedule | Generation
Expected to commence during 2010 |
iv.
3x360 MW COMBINED CYCLE GAS BASED UNIT AT FARIDABAD
The State Govt.
has approved the proposal for setting up 3X360 MW Combined Cycle Gas based Plant
at Navada Koh near Badkhal in Faridabad on 11.08.2005.